Design Construction Architects
Here I will explain all the relevant stages and factors which need to be taken into account in the design stage of construction in relation to the RIBA (Royal Institute of British Architects) plan of work.
RIBA Plan of Work
A Inception
Client establishes basic requirements, cost ranges, timetables, etc. He appoints architect and principle consultants. Basic project organization is established.
Firstly the client will establish the basic requirements, cost ranges, timetables, etc and an architect will be appointed and they will be consulted for his help and professional opinion. The architect will be required to carry out the following jobs.
01 Obtain information about the site from the Client
02 Visit the site and carry out an initial appraisal
03 Assist the Client in preparation of Client's requirements
04 Advise the Client on methods of procuring construction
05 Advise on the need for specialist contractors, sub-contractors and suppliers to design and execute parts of the Works.
06 Prepare proposals and make application for outline planning approval.
The architect will need at least one meeting client and will aim to establish the main parts and general outline of his requirements. It is important for the architect to plan his work so that it matches the fees he is receiving. These fees are charged at a percentage of the overall cost of the project depending on the job type.
At this stage the main financial concern is limitations. This is where money must not be overspent and prices for materials must stay acceptable. It is important that acceptable methods of communication are discussed during the early stages of the job.
B Feasibility
The following processes will be carried out at this stage.
01 Carry out such studies as may be necessary to determine the feasibility of Client's requirements
02 Review the Client's alternative design and construction approaches and the cost implications
03 Advise on the need to obtain planning permission, approvals under Building Acts and or other regulations or other statutory requirements.
04 Develop the Client's requirements.
05 Advise on environmental impact and prepare a report
In this stage the architect will work out whether it is technically possible to construct the motel on our given site. In order to do this the architect will have to obtain information on costs, detailed information on the site and information on the clients requirements provided at the inception stage.
The local authority will be asked to supply us with there standard briefing checklist that will be used to record information. The highway authority will be consulted to carry out checks to determine that there are no problems with access relating to the site. These are all discussed in meetings.
Drawings and models will be produced to help determine feasibility. These will be purely visual aids only and will not consist of construction information or details. After the results of the investigations are gathered, the architect will report to the client and say whether or not it is a feasible proposition to meet the client requirements.
Brief
The brief is the means of communicating the client's requirements to the professionals who will be responsible for implementing the Client's instructions. The instructions may be to a lawyer, an architect, an interior designer, etc. Although there are many forms of brief, the brief for a construction project will be dealt with, in particular, in these notes, but the process and approach is applicable to any brief.
The brief should be based on a systematic appraisal of the Client's requirements. The brief should not be based on preconceived ideas or assumptions. The brief may be developed through discussion and negotiation, which are used to clarify and define the Client's needs. The brief will form the terms of reference for the work to be undertaken by the Professional.
As a set of instructions, the clearer and the more detailed the information supplied, the greater the probability that the service being provided will fulfil the Client's requirements. Thus it is important that a brief gives very detailed information describing precisely the requirements of the Client. The brief, as well as communicating factual information, it should also define the constraints and criteria within which the professional must work. Such constraints and criteria may be the budget, the time scale, etc.
C Outline Proposals
The brief is further developed in line with the general approach to layout, design, construction and services. A cost plan is established. The client is asked for his authoritative approval on how to proceed.
0.1 Analyze the Client's requirements; prepare outline proposals.
0.2 Provide information to discuss proposals with and incorporate input of other consultants
0.3 Provide information to other consultants for the preparation of an approximation of construction costs
0.3 A Provide an approximation of construction costs
04 Submit outline proposals and approximation of construction cost for the Client's approval
05 Propose a procedure for cost planning and control
06 Provide information to others for cost planning and control throughout the project
06 A Operate the procedure for cost planning and control throughout the project
07 Prepare and keep updated a Client's running expenditure plan for the project
08 Carry out negotiations with tenants or others identified by the Client
Here the architect will relate the client's requirements to the information given in stage B. expert advice from structural and building engineers will be sort. The relevant parties will then discuss the various different options given to us This will help us to determine what type of construction would be best for the site on plot j. now the outline scheme drawings can be prepared.
Cost limits of the project will be taken into account by the quantity surveyor, where the architect will help him. Within the cost limits the quantity surveyor and architect will discuss the building standard, which can be provided with these limits.
Indication as to when the building work will start on site and when it is to finish, an outline pre-contract programme will be prepared.
D Scheme Design
The brief is completed and architectural, engineering and services designs are integrated. The cost plan, overall programme and outline specification are developed and planning and other approvals applied for. A report is submitted to the client for his approval.
01 Develop scheme design from approved outline proposals
02 Provide the information to discuss proposals with and incorporate input of other consultant into scheme design
03 Provide information to other consultants for their preparation of cost estimate
03 A Prepare cost estimate
04 Prepare preliminary timetable for construction
05 Consult with planning authorities
06 Consult with Building Control Authorities
07 Consult with Fire Authorities
08 Consult with environmental authorities
09 Consult with licensing authorities
10 Consult with statutory undertakers
11 Prepare application for full planning approval
12 Submit scheme design showing spatial arrangements, materials and appearance together with cost estimate for the Client's approval
13 Consult with tenants and others identified
14 Conduct exceptional negotiations with planning authorities
15 Submit an application for full planning approval
16 Prepare multiple applications for full planning approval
17 Submit multiple planning applications
18 Make revisions to scheme design to deal with requirements of planning authorities
19 Revise planning application
20 Resubmit planning application
21 Carry out special construction research for the project including design of prototypes. Mock ups or models.
22 Monitor testing of prototypes, mock-ups or models.
Now the Design Team will prepare a scheme to show parts of the building as to where they go and what they look like. It will also give a brief description of the materials being used. To do this the architect will have to complete his studies to get the ‘user requirements.' Specialist firms and the design team will decide materials, finishes and services etc.
We will now sort full planning permission and building regulations approval and all effected parties, which will be involved in the site such as highways and drainage, will be notified of our intentions by the local authority.
The architect will now require a cost plan, this will be drafted up with the aid of the quantity surveyor. This will consist of an approximate cost of the project and a separate cost for building 3 and 4. this will then be submitted to the client for his approval. The client will be notified that the scheme cannot change once he has given his approval, and if he does so then this will result in the payment of additional fees.
E Detailed Design
The team designs, co-ordinates and specifies all parts and components, completes cost checks and obtains client's approval of significant details and costs. Specialist tenders may be sought.
01 Develop the detailed design from the approved scheme design
02 Provide information to discuss proposals with and incorporate input of other consultants into detailed design
03 Provide information to other consultants for their revision of cost estimate
03 A Revise cost estimate
04 Prepare Building Notice under building Act and/or Regulations
05 Agree form of building contract and explain the Client's obligations thereunder
06 Obtain Client's approval of the type of construction, quality of materials and standard of workmanship
07 Apply for approvals under Building Acts and /or Regulations and other statutory requirements
08 Negotiate if necessary over Building Acts and/or regulations and other statutory requirements
09 Conduct exceptional negotiations for approval by statutory authorities
10 Negotiate waivers or relaxation's under Building Acts and/or regulations and other statutory requirements.
In this stage of the process the final drawing will be completed and the specification of the building will be completed. The specification will be done by the architectural technologist. The plan of work will be put together. The bill of quantities will be put together by the quantity surveyor from the specification. Information will be provided for the revision of cost estimation also the authorities will be consulted on developed design proposals. The client will approve to the type of construction, the quality of the materials, the standard of workmanship and revised cost estimation. The client will be advised on the consequences of any subsequent changes on cost and programming.
F Production Information
The team prepares working drawings, schedules and specifications and agrees with the client how the work is to be carried out. Specialist tenders may be sought.
01 Prepare production drawings
02 Prepare specifications
03 Provide information to discuss proposals with and incorporate input of other consultants into production information
04 Co-ordinate production information
05 Prepare other production information
06 Submit plans for proposed building works for approval of landlords, funders, freeholders, tenants or others as requested by the Client.
The Architectural Technologist will put together a specification so a tender document can be produced. The production information will be prepared for tender purposes; also schedules will be prepared for rates and quantities. The architectural technologist must prepare and submit under building acts and regulation for the statutory requirements. Building notice must be prepared and given however this is not so in Scotland.
Roles of the Design Team (Task 1B)
Everyone on the design team has specific roles that need to be carried out with care. If a role is not carried out to a specific degree of quality then the offender may be liable for any accidents or damages as this is classed as negligence.
The client;
These are the client's duties however the client may decide to appoint a clients agent. Then the client's agent would carry these tasks out however it is still the ‘client' responsibility to appoint a ‘competent' agent to do the job.
• Appoint a planning supervisor;
• Provide information on health and safety to the planning supervisor;
• Appoint a principal contractor;
• Ensure those you appoint are competent and adequately resourced to carry out their health and safety responsibilities;
• Ensure that a suitable health and safety plan has been prepared by the principal contractor before construction work starts; and
• Ensure the health and safety file given to you at the end of the project is kept available for use.
If you arrange for someone to prepare a design or for a contractor to carry out construction work on the project, you also have duties to ensure they are competent and are adequately resourced to carry out their health and safety responsibilities.
The Architect;
The architect is responsible for defining and maintaining the structure of the solution, and ensuring that it will meet the requirements. An architect must also help the team to work together in an agile fashion, to jointly own the solution, and to interface well with other parts of the organization.
There are five main parts to this:
- Understanding the requirements - identifying the stakeholders, helping to analyze the requirements and extracting those of architectural significance
- Formulating the design - creating a solution structure which will meet the various requirements, balancing the goals and constraints on the solution,
- Communicating the architecture - making sure that everyone understands the architecture. Different people have different viewpoints, so the architect has to present various views of the system appropriate to different audiences,
- Supporting the developers - making sure that the developers are able to realize the architecture, by a combination of mentoring and direct involvement,
- Verifying the implementation - ensuring the delivered system is consistent with the agreed architecture, and will meet the requirements.
The Architectural Technologist;
Architectural technologists work in building design and construction management teams, working especially closely with architects. They form the link between the architect's concept and the completed construction, bridging the gap between the idea of an attractive functional building and the reality of that building performing successfully. They ensure that the right materials are used and that the building meets building regulations and other legal requirements.
They also monitor quality assurance, cost and the meeting of deadlines throughout the lifetime of a construction project. Fully qualified members of the Chartered Institute of Architectural Technologists (CIAT) can take total responsibility for the management of a project.
The balance of different activities varies according to the kind of projects and the size of the organisation. However, typical work activities usually include:
• Meeting with clients and other involved professionals at an early stage to agree the project brief;
• Understanding how the design aspects of a construction project influence and relate to performance and functional issues, so that practical questions can be addressed at an early stage;
• Evaluating environmental, legal and regulatory issues and advising on these;
• Contributing to planning applications and other regulatory application procedures;
• Assessing what surveys (e.g. land surveys) are required before work can commence and ensuring such surveys is undertaken and their results fed into the project;
• Developing project briefs and working on these as the project progresses;
• Preparing and presenting design proposals using computer-aided design (CAD) and traditional drawing methods;
• Leading the detailed design process and co-ordinating design information;
• Advising clients on procuring the best and most appropriate contracts for the work they are undertaking;
• Liaising with appropriate authorities (e.g. planning enquiries and building inspectors) when producing documentation for statutory approval;
• Producing, analysing and advising on detailed specifications for suitable materials or processes to be used in construction;
• Carrying out design-stage risk assessments;
• Administering contracts and project certifications;
• Obtaining feedback on work in progress and finished results from clients;
• Appraising the performance of buildings which are in use and producing maintenance management information;
• Evaluating and advising on refurbishment, re-use, recycling and deconstruction;
• Managing the work of trainee technologists;
• Contributing to the overall running of business.
Landscape Architect;
Landscape architects/designers are essentially designers of outdoor spaces, of any land open to the sky, including land lying around and between buildings. They work to ensure that any changes made to the natural environment are appropriate and sensitive, as well as innovative and aesthetically pleasing.
Projects can be both urban and rural and range from designing the layout of parks, gardens and housing estates to improving land affected by mineral extraction or motorway construction. The work involves collaborating closely with landscape contractors, as well as other professionals, especially architects, and those working in surveying and engineering functions.
Structural Engineer;
A structural engineer designs structures that will withstand the pressures they have to endure. These may be buildings, aerials, bridges, oil rigs, aircraft; anything from a playground climbing frames to the tallest building. They develop initial designs, using mathematics to calculate the stress that could arise at each point in the structure, and simulate and model possible situations, such as high winds and earth movements. When construction has commenced, they are often involved in inspecting the work and advising contractors.
These engineers often work in partnership with architects. They also examine buildings, bridges and other structures to discover whether or not they are structurally sound.
Services Engineer;
A building services engineer is responsible for ensuring the cost-effective and environmentally sound design and maintenance of energy-using elements in buildings. They have an important role in developing and maintaining buildings, and their components, to make the most effective use of natural resources and protect public safety. This includes all equipment and materials involved with heating, lighting, ventilation, air-conditioning, electrical distribution, water supply, fire protection, safety systems, lifts and escalators, and even acoustics.
Whilst the role increasingly demands a multidisciplinary approach, building services engineers tend to specialise in one of the following areas:
- Electrical engineering;
- Mechanical engineering;
- Public health.
Stages of Project Planning Process (Task 1C)
Planning Team
The project team can be very important and it is essential to show that the team have the relevant experience, skills or training. It is often necessary to employ people who have been associated with similar projects previously. The experts may be expensive or may have limited availability, in which case the expert can be appointed as an advisor and may not have a great input. It is important not to mislead the Client by indicating a greater input than there will be in reality.
G Tender Documentation
This is the first part of the planning stage. Here, the contract documents have been signed and any matters that have not been signed will be discussed between the architect, the client and the contractor. Both the client and the architect have rights and responsibilities where they must understand their own roles in the project. The client will be the employer and the architect will be the employer's agent. Really this meeting will sort out the roles and responsibilities of everyone and a checklist may be used so that nothing is forgotten.
H Tender Action
Main contract tenders are obtained by negotiation or competitive tendering procedures. The client is asked to agree that suitable tenders are accepted.
01 Advise on and obtain the Client's approval to list of tenderers for the building contract
02 Invite tenders
03 Appraise and report on tenders with other consultants
03 A Appraise and report on tenders
04 Assist other consultants in negotiating with tenderer
04 A Negotiate with a tenderer
05 Assist other consultants in negotiating a price with a contractor
05 A Negotiate a price with a contractor
06 Select a contractor by other means
07 Revise production information to adjust tender sum
08 Arrange for other contracts to be let prior to the main building contract
The contractor will be given a list of firms that the architect is considering using including the ones named at the tender stage. The architect must ensure that the contractor has no objections with any of the firms involved.
The subcontractors and suppliers will receive letters telling them that they have been successful or unsuccessful. The contractor will then be informed to accept the sub-contractors quotation. When the architect has the meeting with the contractor he must make sure the agreement has been completed the clauses have been deleted from the conditions as appropriate. The signing of the contract includes many operations such as checking the contractors insurance and sending the contractor a copy of the contract.
J Project Planning
Contract documents are processed. The contractor receives information needed to plan the work. The site inspector is briefed and all roles are defined. The site is made available for work to start.
01 Advise Client on the appointment of the contractor and on the responsibilities of the parties and the Architect under the Building Contract
02 Prepare the building contract and arrange for it to be signed
03 Provide production information as required by the building contract
04 Provide services in connection with demolition
05 Arrange for other contractors to be let subsequent to the commencement of the building contract
Production information must be ready for the project meeting. This is the meeting that takes place before any work starts on site. The project information will be made up of two copies of the drawings, schedules and specifications. Copies of statutory approvals and the architect and contractor programme will be needed.
K Operations on Site
Contract is administered and contractual obligations fulfilled with progress and quality control monitored. Financial control, with regular reports to the client, is maintained.
01 Administer the terms of the building contract
02 Conduct meetings with the contractor to review progress
03 Provide information to other consultants for the preparation of financial reports of the Client
03 A Prepare financial reports for the Client
04 Generally inspect materials delivered to site
05 As appropriate instruct the taking of samples, carrying out of tests of materials, components, techniques and workmanship and examine the conduct and results of such tests whether on or off site
06 As appropriate instruct the opening up of completed works to determine that it is generally in accordance with the Contract Documents
07 As appropriate visit the sites of the extraction and fabrication and assembly of materials and components to inspect such materials and workmanship before delivery to site.
08 At intervals appropriate to the stage of construction visit the Works to inspect the progress and quality of the Works and to determine that they are being executed generally in accordance with the Contract Documents
09 Direct and control the activities of site staff
10 Administer the terms of other contracts
11 Monitor the progress of the Works against the contractor's programme and report to the Client
12 Prepare valuations of the work carried out and completed
During the early stages of project planning, it is important to identify the resources and schedule for development of the Maintenance & Operations Plan. The roles and responsibilities of the various resources must be determined and an overall approach developed.
Most project processes will have maintenance and operations equivalents, including change management, governance processes, testing and communications. Employers need to review Project planning elements to determine those needed on an ongoing basis and include them in the Maintenance & Operations Plan.
A risk assessment will have to be carried out for each operation that will occur on site. This determines what PPE the person will have to wear and how big the risk is of carrying out this operation. A check list will have to be made so that all equipment can be checked over once and a while. For example, the oil level in generators must be checked weekly so that they are able to run smoothly on site. A checklist can be ticked off once the generator has been checked and is in good working order.
L Completion
Project is handed over for occupation. Defects are corrected, claims are resolved and final account is agreed. Final Certificate is issued.
01 Provide drawings showing the building and main lines of drainage
02 Arrange the drawings of building services installations to be provided
03 Generally give advice on maintenance
04 Prepare drawings for convincing purposes
05 Compile maintenance and operational manuals
06 Incorporate information prepared by others in the maintenance manuals
07 Arrange maintenance contracts
This is the stage where the building is handed over to the client so that it can be occupied, rented etc. All remediation is done to any thing that's is wrong within the project. The final account should be signed by the client to say that he is happy and that there is nothing else to be done. The architect also needs to sign it. It also means that everything has been done according to the contract.
M Feedback
The performance of the building and the design and construction teams are analysed and recorded for future reference.
This stage also mentions that after the building has been finished, the architect and the contractor are responsible for any failures that may occur to the building in the near future. However, it is obvious that if the failure occurs in the far future then this not their responsibility.
At the end of this stage there are many questions asked. These include things such as,
- Did the contractor work well?
- Does the building function properly?
- Did the design process work smoothly?
- What does the client think of the building?
Factors that effect planning decisions (Task 1C)
There are many things that need to be taken into consideration when making planning decisions, all projects produce different factors to be considered such as the following;
- Budget
- Availability of materials
- Availability of workers (Hiring sub contactors)
- Weather
- The Planning (conservation areas & listed building areas) act 1990
- The Town and Country Planning Act 1990
- Restrictions on the land/local area
- Usage of development
- Surrounding infrastructure
- Existing Access
- Who will be using the facility e.g. old people or disabled
- Demands of the client
- Building regulations
How to overcome these factors
1) Analysis of the Problem Breakdown the problem into simple components which may be easily managed. Create a flowchart in the form of a decision tree. Each stage of a project and all possible options are shown so as to produce a series of outcomes.
2) Assessment of Outcomes. This is based on utility (the relative desirability) which is assessed for each possible outcome. The criteria are listed and their relative importance is evaluated. Each outcome is assessed against each criteria and then is evaluated by summing its utility score against each criteria weighted by the relative importance of each criteria.
3) Assessment of Probabilities. The alternative outcomes of each decision stage are allocated probability of the likelihood of their occurrence. These are subjective assessments, but experience is used to lend some objectivity.
4) Determining Optimum Path The optimum path through the decision tree is determined by working backwards from the final outcome and calculating the expected (weighted average) utility of each event node. Where several activities enter an activity event node, the path with the highest utility is elected and the others are eliminated. The best path through the decision tree is found.
5) Sensitivity Analysis Important elements of the decision tree should be assessed by applying a range of values to determine the effect.
Decisions to be made for this project (Plot J)
Budget
The budget for the project and the program for implementation will be very difficult to ascertain at this early stage, but if some indication can be given and an approximate cash flow, it could be very useful to the Client and would indicate our understanding of the project.
In order to ensure my project comes in on budget I will be employing a skilled and experienced quantity surveyor. This is because there is a big difference between estimated costs and true costs, which would be calculated to a degree of accuracy by the quantity surveyor. Budgets for the professional fees and program's for the professional services would also be useful.
Green Field site
As our site is situated on a “green field site” then there will be certain implications which may hamper the development.
- Once land has been converted to development, it is unlikely to ever be converted back to Greenfield use
- Destruction of the natural habitat of some animal and plant species
- Loss of agricultural land results in loss of production and loss of employment
- Reduction of or complete loss of amenity or recreation value
- Negative effect upon transport and energy use
- Loss of the green belt of agricultural or designated wildlife land, that clearly defines and separates areas of difference, be they cities, towns, suburbs, villages or hamlets of housing
Restrictions on development and Leases
As our site is located on a Greenfield site therefore it has not been built upon before and our development is the 1st on the site then therefore as long as the local authorities accept planning permission then there are no restrictions as to what we can build. Where as if this was a brown field site that had a restaurant then there may have been a lease so that the site could only be used as a restaurant.
Also the local authorities have also said that there are no restrictions on our roof designs. Therefore this leaves us in a good position to come up with something suitable, attractive and original whilst also maintaining our budget.
Trees (TPO's)
As it is a Greenfield site there is as expected trees on the site. It is the duty of the local planning authorities to preserve trees. It is an offence to cut down, lop, top or willfully damage such trees without the consent of the local planning authorities unless they are deemed to be dangerous, dying, dead or the work Is executed in compliance with another act of parliament. Prior consent should always be sought.
In order to save time but to also create a nice environment around the site I will be trying to include as many of the existing trees as possible. This will create an attractive environment for the people staying in the motel. Also the local authorities would also appreciate this as it would allow the development to fit into the local surroundings.
Access, Services and Infrastructure
As I have already been given a site layout plan then the position of the buildings and the road access has already been established therefore when designing the buildings I will have to make sure that the fit into the plots provided.
However I will have to decide on where the services will come into the site. This includes water supply, gas, electricity and drainage. The services generally follow the path of the road into the site so therefore this won't take much planning as the road layout is already set out. However I will determine where the services will enter the buildings and also the relevant terminals.
Accessibility to all
As the motel will be used by everyone such as young children, elderly and the disabled then by law we will be required to provide the appropriate access, services and accommodation so that it can be used by all.
In the motel I will be included appropriate access facilities such as lifts, hand/ rails, ramps and also disabled parking. This will ensure that all persons can move around the motel freely and safely.
I will also be incorporating special rooms which will provide appropriate accommodation for all. These will include special equipment such as disabled bath and toilet facilities for the disabled and also family rooms which will provide appropriate baby changing facilities.
Time factors that Bear upon the Design and Construction of the Project (Task 1D)
In order to ensure that a project is completed on time then the project team need to stick to a strict schedule. However with every project there come delays whether it is of human or natural causes. Some allowable time should be placed on a project in order to cope with this however there are still sometimes heavy delays. Here are a few delays, which may occur;
- Availability of materials
- Delays on materials
- Subcontractors not being able to meet deadlines
- Unforeseen problems (ground conditions)
- Weather
- Injuries and sickness of employees
- Machinery breakdowns
- Employees making mistakes that cost time and money
How these may affect my project located on plot J
Materials
The length of time the project will take for completion relies heavily on the how long it will take for the materials, required, to reach the site. If the project requires rare or specific types of material then these may need to be imported from other countries, which would take up valuable construction time. Damaged or faulty materials would also cause delays in construction.
For instance if the specified roof tiles are made in Italy to specific requirements and the delivery is delayed or the materials are damaged, then this would mean that the roofers would then be behind schedule which in turn could mean that the decorators could not get in to do there job, this means that any delays have a nock on effect for other stages of the construction, creating more delays.
In order to reduce the likely hood of massive delays in the arrival of materials to our site on plot j, we will, where ever possible and feasible, only specify materials that are produced or are widely available inside the UK. We will also only deal with suppliers that have a good reputation for delivering goods on time and in sound quality.
Contractors, Subcontractors and Employees
The reliability, punctuality and efficiency of all site workers contributes hugely to the overall construction time. If a job on site isn't completed on time then this has a nock on effect to the people who are carrying out the next stage of construction. This may occur where persons become inefficient, incompetent or where there are absences due to health reasons.
For instance if an electrician takes ill and has to take time off, then the electric's wont get installed on time therefore the plasterer wont be able to get in to plaster the walls. All of this effects hugely whether the project meats deadlines and stays on timetable.
In order to reduce the risk of becoming behind schedule as a result of contractors, subcontractors and employees, we will ensure that only competent, experienced and reputable workers will be hired. As we can't prevent people from taking ill and therefore sick leave, we will also ensure that we have the resources to cope with minor workforce issues.
In order to keep a happy work force which will produce good quality work, on time there will be an incentive scheme. This will ensure workers receive a small bonus for meeting deadlines. This gives workers a reason to work hard for the project therefore producing quality results on time.
Unforeseen Ground Problems
It is said that as many as 25% of construction and engineering projects are delayed by unforeseen ground conditions. Whilst this percentage may appear high, the really surprising issue is the inconsistent way in which standard forms of construction contract seek to deal with the problem. There is no single set of rules which govern the discovery of unforeseen ground conditions and no acknowledged ‘best practice' when it comes to risk allocation and procurement practices.
The starting point is the initial ground investigation report. These reports are all too often hopelessly inadequate. They are procured at minimum cost, sampling at best a tiny fraction of the site, and often prepared in isolation from, and in ignorance of, the intended development of the site. The responsibility for preparation of the initial ground investigation report rarely lies with the party who will carry out the structural design of the project. This contributes to an uncertainty over the allocation of the risk of adverse ground conditions which pervades almost all construction contracts. If the ground investigation has been carried out in this isolated and superficial manner, it is inevitable that its author will heavily qualify his findings and disclaim responsibility for any errors or omissions in the report. Plainly, in such circumstances, the value of the report will be minimal. Moreover, the contractor may be unable to carry out more extensive site investigations during the period available to prepare his tender.
In order to reduce the possibility of delays to our project due to unforeseen ground conditions I will carry out a site investigation following the steps as follows.
Weather
Harsh weather conditions mean that construction may have to be suspended. This is because it may not be safe for work to be carried out. This therefore results in deadlines not being met. This is a huge problem on any construction site in any country, however as weather can not be controlled then it is something that the construction industry has to live with.
An example of this is if it is very cold and there is a lot of frost then bricks can not be laid as the cement will crack and crumble. Also if there is heavy rain then the site can become very muddy and slippery therefore it would not be safe to work on as a worker may slip and fall.
Although we can't control the weather we will do our best to prevent the effects of it. We will ensure the site has good drainage so it therefore does not become flooded. Bricks, machinery and cement etc will be kept under cover therefore reducing the likely hood of them becoming frosted, and failing.
Task 2A - Evaluate the standard methods used to determine the plant required for the construction of buildings 3 and 4. The evaluation will need to include at least the following:
• Range of construction plant considered
• Characteristics and use of suitable plant
• Cost versus hire options
• Time and labour savings
• Implications for programming methods
Range of Construction Plant
Here are just a few pieces of equipment that are used on construction. I will explain the characteristics of the plant and also how they may be useful on our site.
Cement mixers
Cement mixers can be seen on almost any construction site. They range in size from the smaller ones shown in the picture to large cement mixing trucks. The larger trucks are usually used to fill in foundations and the likes, whereas the smaller cement mixers are generally used for traditional methods of construction, generally by bricklayers.
We will use large mixers to supply the site with cement for the foundations. The mixers fill up at a local cement mixing sites meaning there is less time wasted mixing it on site.
Generators
Generators are used to create electricity for various different pieces of equipment on a construction site. From the kettle in the cabin to drills and welding equipment. The size of the generators depends mainly on the size of the site and how much power they will need, from small box generators to large units.
Backhoe
Whether you need to dig a basement, install drainage, pick up dirt, or load cut timber onto a truck, a backhoe will be able to perform the work as you require it. True, the work could also be done by a team of strong men equipped with the right tools. a backhoe will get the job done in a fraction of the time.
Whenever there is a need for excavation, the shovel bucket attached to the backhoe will operate effectively. The backhoe can dig up even the hardest and most compact materials. The bucket can be raised and swung by an operator to deposit excavated material anywhere. This piece of heavy equipment is ideal for foundation and installation work.
Modern backhoes are powered by hydraulics. Most backhoes are currently turbocharged and diesel-powered. Backhoes move with ease over rough terrain thanks to their large, rugged tires. Since they have both excavating and loading sides, they can be used to load large amounts of minerals and any other kind of loose material onto a truck or container. The front-loading attachment can also be used by the operator to smooth surfaces or push things around. Backhoe loaders can also be equipped with brooms, rakes, forks and a wide range of attachments to suit specific needs. Backhoes are mainly manufactured by American companies, although a few British and Japanese companies also produce them.
Impact crushers
Impact Crushers can crush mining stones and rocks. These are used to grind down the hardcore on site. The hardcore is then used to level off the site and also to provide a hard ground surface. Impact Crusher is mainly suitable for building materials, transportation, energy, cement, mining and chemical industry.
Roller
The roadways will have hard core laid in them to stop vehicles slipping through out the course of the project and if they are to become permanent roads they will be tarmac also. To compress the hard core a role will be required to produce a solid level surface that is easy for large wagons delivering goods to use.
Dumper
A dumper is a four-wheeled open vehicle used to move bulk material on industrial job sites or for smaller construction and landscaping jobs. Often referred to as power buggies, these vehicles help in a variety of tasks such as concrete pouring and dumping, construction debris removal, landscaping, and on-site tool and equipment transportation. These vehicles are also used in cemeteries, golf courses and nurseries. The load skip is integrated in front of the driver and is used to dump the load. This is why the machine is known as a “dumper”.
Initially, dumpers were rear wheel drive vehicles. This diesel operated engine was started by hand cranking, while the skip was secured by the driver's feet. As soon as the catch was released, it would be emptied at the desired place and raised by hand again. A modern day dumper can have a capacity of up to 10 tonnes. The dumper has a multi-cylinder diesel engine or a turbocharged engine. They have an electric start with hydraulics for tipping and steering. A dumper may have various features such as the ROPS (Roll-Over Protection) frame and FOPS (Falling Object Protection). Some dumpers have lifting skips that help discharging the material above ground level.
Buying Versus Hiring
I feel it would be worth while for the contractor to buy the items of plant that would be used regularly on all sites. Therefore they can use them for other jobs. These pieces of plant would include a backhoe, small cement mixers, and generators.
Plant such as large excavators, rollers, cranes and impact crushers would be hired. This is because it wouldn't be cost effect to buy these and they wouldn't be used regularly, which also means storage facilities would have to be supplied.
Programmes
A master program will have been established during brief development at Stage 1, including the time that the design team assesses as reasonable for the construction process. This time period will be stated within the Construction Contract documentation, and it is the contractor's responsibility to arrange the progress and sequence of works, to achieve completion within this period. It is a normal contractual requirement for the contractor to develop a detailed construction programme, setting out the sequence and duration of all the different construction activities, and highlighting critical path elements associated with the construction process to ensure and demonstrate that expected delivery timescales are met In defining the construction period within the master programme, the client may also have identified whether there are any circumstances (relating say to financial or operational issues) whereby access to certain parts of the project will be necessary prior to formal completion and handover of the project as a whole. Any such requirements will need to be discussed and agreed with the appointed contractor (if not identified within the tender documents), as they may impact on intended progress and sequence of working.
In order to construct any facility, the main contractor will have to establish and co-ordinate a supply chain of sub-contractors, suppliers and specialists. Establishment of this chain will closely relate to the critical path element in the contractor's programme, ensuring timely availability and delivery of main construction elements such as steelwork, bricks, windows and doors, identifying goods and materials that require long lead times, and availability of sub-contract labour at the appropriate stage in the contract.
Forms of Low rise Building (Task 3A)
The choice of building types is more often than not the result of economic considerations, such as land values, land availability and the cost of infrastructure. However, each building type and combination of different types interacts with local environmental conditions in a different way, which affects both the microclimate around the building and that inside it.
Listed below are the concepts that should be taken into consideration when designing a building.
Human Comfort
Environmental efficiency
Aesthetics
Durability
Stability
Low-rise construction is a structure made of just one or two storeys. These are the common forms of low rise construction in relation to there frame.
• Portal frame construction.
• Cross wall construction.
• The two forms of Timber Frame Construction which are Balloon Frame & Platform Frame.
• Cellular construction.
• Skeleton Frame construction.
• Brick and block
Portal Frame construction
This type of building, sometimes described as an 'umbrella' building, is usually constructed of steel portal frames (steel columns and rafters), spaced 4.8 to 6 m. apart and with a clear span of 10 to 30 m. The infill walls between the columns are filled with brick or concrete blocks and/or steel, fibre-cement or timber cladding, and the roof covered with steel or fibre-cement.
The advantages for PLOT J are:
· Rapid construction. The frame can be normally be erected in a day and the roof cladding in a week which then protects the site from the weather and allows walls, floors and internal fittings to be completed without interference from poor weather conditions.
· Clear space. Since the internal layout is independent of the walls and roof, any arrangement of internal divisions and fixtures can be accommodated.
· Versatility. The use of the building can be changed at any time to meet changing farming policies by simply removing or adding divisions.
This form of design reduces the bending moment in the beam which allows the frame to act as one structural unit. The beam transfers the stresses of the load to the column; this can cause movement at the foundation, this can be overcome by the installation of a hinge joint. This would allow free rotation to take place at the point of fixity. Portal frames are primarily used in single storey construction as it provides unobstructed space between the floor level and rafters.
Cross wall construction
Cross-wall is a generic method of building construction using a series of division or party walls which transfer the floor loads through the building to foundation or transfer slab level. The cross-wall system generally utilises stair cores and lift cores for overall stability, using the floors as stiff diaphragms for the transmittal of horizontal forces into shear walls located at staircase and lift shaft positions. The floors are made up of hollow core, solid slab, or composite construction.
This type of construction is suitable for structures up to five storeys high. For a build such as a motel as proposed on PLOT J. Due to this form of construction being highly efficient. An ideal material for cross walls construction is dense cast in situ concrete.
Timber Frame Construction
Timber frame construction is a method of construction that uses timber studs and rails, together with a wood based sheathing, to form a structural frame which transmits all vertical and horizontal loads to the foundations. The external cladding is used purely for wind protection and waterproofing which is not load bearing.
Generally in the UK we use factory manufactured wall frames and roof trusses when using the timber frame construction method. The extent of factory prefabrication can and does vary considerably; from so called ‘open panels' consisting of simple sheathed stud panels with a breather membrane, to ‘closed panels' which include insulation and internal linings and may also include components such as joinery and sometimes also cladding. Floors and roof panels may also be factory-prefabricated as open panels with simple joists or rafters and sheathing panels, or as closed panels with insulation, linings etc fitted in the factory. The selection of an appropriate arrangement is an early decision in the design process.
Timber frame primarily developed in the UK for house building although it is also widely used for buildings such as hotels, hostels, clinics, nursing homes, student accommodation, offices and similar structures.
Platform frame is the most commonly used method in the UK. Each storey is framed with floor-to-ceiling height panels and the floor deck of one floor becomes the erection platform of the next.
The prefabricated wall panels can be either small units (up to approximately 3.6 m in length), designed to be manhandled into place or up to full elevation-width panels incorporating ancillary components for placing with a crane.
Floor-to-floor panel frame: this is an erection method whereby the wall panels (except for the topmost storey) are floor-to-floor, or storey height, rather than floor-to-ceiling and the intermediate floors are hung inside the wall panel. This reduces cross-sectional shrinkage of timber in the external wall and enables the insulation and vapour control layer to be continuous up the wall face.
Volumetric: involves the factory fabrication of box units which can form individual rooms, or larger spaces complete with finishes and services and which require crane erection. This is best suited to repetitive units, such as hotels, hostels or nursing homes.
Post and beam: comprises a load bearing system of posts and beams with lightweight timber or glazed infill panels. In the UK, this tends to be used in the specialist 'traditional appearance' market but there are modern timber frame systems using post and beam elsewhere in Europe.
Skeleton frame construction
Skeleton frame construction predominantly uses a steel structure. This comprises of a series of rectangular frames placed at right angles to one another in order to transmit a load from one member to the next, then projected onto the foundation. Skeleton frames consist of either one of two materials which are either concrete or steel (although timber can be used). The choice of which material may depend on a series of different considerations, these include cost implications, timescale, availability of labour, site conditions.
The frame needs to be protected from fire because steel softens at high temperature and this can cause the building to partially collapse. In the case of the columns this is usually done by encasing it in some form of fire resistant structure such as masonry, concrete or plasterboard. The beams may be cased in concrete, plasterboard or sprayed with a coating to insulate it from the heat of the fire or it can be protected by a fire resistant ceiling construction.
The exterior "skin" of the building is anchored to the frame using a variety of construction techniques and following a huge variety of architectural styles. Bricks, stone, reinforced concrete, architectural glass, sheet metal and simply paint have been used to cover the frame to protect the steel from the weather.
Cellular Construction/Box Construction
This is a method of building with concrete in which individual cells, or rooms, are set horizontally and vertically together to create an overall structural frame. Because the main weight of the building is carried through the cross walls, they must be sufficiently thick to carry their own weight as well as loads from above, and so the potential height of a structure built in this manner is limited.
This structure proves to be rigid, durable and stable, also it is a quick and effective form of construction and the rooms can be easily divided up. With each of the walls being of load bearing quality this furthers the expense of the building. A cellular structure building's walls usually comprise of cast in situ concrete.
I believe this form of construction would be ideal for our site on PLOT J. this is because when a building is prefabricated in factory conditions then there is huge difference in construction time. It also helps to prevent delays to the schedule due to unseen circumstances such as weather. Cellular construction is also very suitable for buildings such as motels and hotels because all of the rooms such as bathrooms, shower rooms etc can just be simply multiplied and uniformed.
However using this type of construction does tend to be very expensive as it takes a specialist fabrication firm to carry this out. Also if the contracted fabricator is unreliable then this will drastically slow down construction. Brick and Block
Brick and block super structure are often built upon strip foundations as each brick and block rests upon the foundation to transfer the load safely to the ground. Brick and block work is erected on site brick by brick, block by block. There are two main factors that affect the strength of brick and block work. The mix of mortar to hold the bricks and blocks together and the bond used. There are many different forms of bonds.
English Bond
This is bond is created by running a course of stretcher bond followed by a course of header bond alternatively. This bonding method is mainly used in a one brick thick wall - 215 mm wide. This is one of the strongest types of bond but also uses the most bricks, typically 89 bricks per m². The image below shows this bond.
Flemish Bond
This bond is formed by running a course of alternate stretchers and headers on each course which is then repeated in each successive course. This method is one of the more I pleasing bonds and is favoured for architectural effect. This method of bonding is not as strong as English bond it uses less bricks though. It uses approx 79 bricks per m².
Special Bonds
Flemish Garden Wall
This bond is created using one header to every three stretchers on each course, this is then repeated on subsequent course but ensuring in each case that no straight joints appear.
English Garden Wall Bond
This bond is created using a course of header bricks followed by three courses of stretcher bricks. It gives a better spread of imposed loads and also uses less bricks than English bond.
English cross bond
Rat Trap Bond
Uses bricks laid on their edge, with hollow pockets between each successive brick on each course. The pattern is then repeated in subsequent courses. This reduces the overall mass of the wall and also allows ventilation to take place in areas below floors etc.
Forms of construction to be used for buildings 3 and 4
Building 3 Timber Frame |
Building 4 Brick & Block |
|
Durability |
In suitable environments, and/or with suitable protection, timber is extremely durable and can last indefinitely. However, poor specification, poor design and detailing can result in rapid degrade. The main agents of deterioration in timber are fungi, insects and ultra-violet radiation. Timber left exposed to the weather and light will lose its color and become grey and the surface may become woolly. Some form of protective finish is needed to maintain the bright appearance of timber when used either externally or internally. External finishes may be paints, exterior wood stains or varnishes. Preservative treatment in itself does not confer surface protection. |
We have been using the Brick & block method in construction for many years, and it has been very efficient due to the low maintenance factor. The brick and block method has proven to last for hundreds of years therefore it is more than adequate for our purpose as the motel only has a life expectancy of 25 years The only main problems involving the brick and block method are weathering by frost Brick and block work can be susceptible to frost heave and weathering of the bricks or stone depending on type of stone or brick. Lime stone is susceptible to weathering. The only other durability factor is that the brick mortar may need re-pointing now and again in order to keep its water tightness and also to prevent it from becoming structurally unsafe. However this does not need to be carried out often. |
Stability |
Diagonal bracing effectively triangulates critical parts of rectangular frame and resists the tendency of 4-pin structures to adopt a parallelogram or to 'rack'. Timber braces of adequate cross section will work in tension and compression and are often used as single braces eg knee braces to keep the construction simple and consistent. Thinner steel rods will buckle in compression but are useful as tensile cross bracing to achieve a lighter appearance, perhaps across a complete bay. |
Brick and block work is ridged giving it good structural properties against deforming and warping. Brick & block work is a solid form of superstructure, However if movement is the substructure take place unsightly cracks can apiary on the superstructure. It has been known for fronts of buildings to collapse due to this. The strength of the bricks will determine the dead loads, imposed loads and life loads. Brick and block work is highly resistant to fire and can resist fire damage. |
|
Human Comfort |
Adding 30mm plasterboard to a timber frame construction generally gives good sound insulation however adding mineral wool into the cavity would give increased sound values. And of course, the thermal efficiency of timber frame homes is legendary - providing homes that are very comfortable and require a lot less energy to heat. Timber frame developments regularly achieve ‘Very Good' and ‘Excellent' ratings under EcoHomes. It is very important to make sure a timber frame building is properly ventilated to ensure that the timber doesn't rot. Also timber frame buildings can become very stuffy in warm climates, therefore correct ventilation is necessary to provide a comfortable living environment. |
Brick & block has extremely good thermal values, especially when constructed using a cavity and insulation. To provide adequate sound insulation to comply with building regulations for walls the mass of block work cavity is increased from 250Kg/m² to 300Kg/m². Also for floors the mass of the floating concrete floor base is increased from 220Kg/m² to 300Kg/m². Also double layered plaster board can be used to help increase sound insulation. Windows can easily be placed into the brickwork in order to supply the rooms with enough natural light. Sills and beams maybe placed above or below the window to supply the structure with more support. Louvers can also be placed into the window frame which gives the building good ventilation. A fresh air supply must be present in most buildings. Other ways to provide this ventilation include mechanical ventilation. Ducts will be strategically places around the building to aid ventilation. Keeping the superstructure ventilated will also help keeps the building dry reducing the risk of damage from damp. |
Environmental Efficiency |
Timber is an organic, non-toxic and naturally renewable building material. Although worldwide, deforestation remains a significant issue, it is not caused by the European construction industry which mainly uses softwood. Over 90% of all wood consumed in Europe is sourced from European forests. UK timber frame uses 99% European softwood. The more wood we use, the more our forests grow, because in Europe we are committed to planting more trees than we harvest. Every year our forests grow by over 3,500 square miles - equivalent to an area the size of Cyprus. Forests act as huge carbon sinks. The total carbon sequestered in Europe's forests is over 9.5 million tonnes. |
Brick and block work have good insulating qualities along with the insulation used with in the cavity wall the building will use loss less heating emissions. Also using recycled or reclaimed bricks would help make the building more sustainable. |
|
Aesthetics |
Brick, stone, timber or render can be used as the outer leaf of a timber frame building. The outer leaf is purely for weather shield and aesthetic purposes and has no structural role. |
Traditionally the Brick is what is seen from the outside of a brick and block building. However different stones can be used, the building can be rendered, painted or even pebble dashed in order to give the building a more distinguished look. |
Annotated sketches of traditional and modern methods of construction (Task 3 B)
Infrastructure needed to support the construction process (Task 3 C)
Timber frame
A timber frame erection team will erect the frame using a crane and a telescopic platform. The timber frame will be prefabricated in a factory and all the installation will take place on site. Once the structure is made water tight then other works can begin.
If a stud wall is to be built scaffolding will be required much like the traditional method. A telescopic handler may also be used. For the brick façade, brick laying squads will be needed and pulley systems will be needed to transport small tools and mortar to the upper scaffold. Also a mixer may be required to mix the mortar.
The internal walls of the frame will also be made from timber. The plasters will be able to layer plaster board directly onto the internal frame. A glazing team will lift the windows into place using a crane and a telescopic platform. Any external doors will also be fixed. Second fix joiners will be required to fix internal doors and finishes.
Brick and Block
To make the traditional form chosen possible to build people and plant will be needed. To start brick layers will be needed as well as a cement mixer.
Once the brick and block work is beyond a reachable level scaffold will be needed to continue the work. Pulley systems will be needed to transport small tools and mortar to the upper scaffolding.
A crane may be required to lift window sills to upper floors as well as lifting roof trusses into place. There crane can also be used to lift materials to upper floors and the roof e.g. Roof tiles.
When the floors are ready to go into place a team of first fix joiners may be needed to lay floor boards and connect the floor joists using bracings.
If a concrete floor is to be used a concrete laying gang and a concrete pump with a boom arm may be required to reach inside the building.
The joiners may also take part in connecting the roof trusses and make it possible to lay the roof covering.
The first fix joiner will build any stud walls inside the building providing a level surface for the plaster board to be fixed in place. These joiners will leave provision for services. A glazing team will install the glazing units and for upper floors this will require the use of a crane. The glazers may also fix external doors.
Compare 2 Techniques to Construct the Superstructure (Task 3 D)
Building 3 Timber Frame |
Building 4 Brick & Block |
|
Sustainability |
In order to make the timber frame construction sustainable, for every tree used in the construction of the building then there will be at least one tree planted |
Using recycled or reclaimed bricks would help make the building more sustainable. |
Cost |
Timber Frame is an extremely cost effective method of construction. The following figures, which have been collated by the UK Timber Frame Association, highlight the potential cost benefits: Timber frame has a 30%shorter, more predictable construction time than brick and block. This means a faster return on investment, reduced disruption to local communities, tidier, safer and more efficient sites. A typical timber frame house can be weather-tight in less than 5 days. In addition, when you come to sell your new building development you can boast that wood is a highly effective insulating material. This can result in average fuel maintenance costs as much as 40% less than traditional build. |
No intensive cost exercises have been done on a comparison between a Timber Frame structure and a traditional brick and block structure. On a material only basis timber frame does work out more expensive on paper but there are many other aspects to take into account. |
Ease of erection |
The installation of a standard 3/4 bed house will take on average 7-10 working days. When the erectors leave site you will be left with a complete structural shell including wall panels, floors and roof trusses that are braced. The first job for the client to do after the erectors leave site is to bring in the roofing company to felt, batten and tile the roof to make the structure watertight and put a loading on the frame. Various trades can then be brought in to work both inside and outside the structure at the same time. |
The construction of a brick and block is very time consuming. This is because bricklayers have to work on-site. The traditional method takes longer to construct and finish as the actual building operation is more painstaking, the houses literally being built brick by brick. In many cases the necessity to have wet trades both externally and internally mean that a longer time is needed to build |
|
Performance in place |
If treated properly Timber frame construction can provide a structurally sound building. However the life expectancy of a timber frame construction maybe considerably less that other methods of construction. However our motel only has a life span of around 25years. |
Brick and block is proved to last hundreds of years, and it is a very structurally sound form of construction. The solid mass of a brick and block self build allows the absorption of heat, which is radiated into the house. This creates a more stable temperature meaning less heat will be required at night. Tests have shown brick and block built houses to maintain a temperature between 5°C - 8°C higher than lightweight structures. |
Environmental impact |
Although worldwide, deforestation remains a significant issue, it is not caused by the European construction industry which mainly uses softwood. Over 90% of all wood consumed in Europe is sourced from European forests. UK timber frame uses 99% European softwood. The more wood we use, the more our forests grow, because in Europe we are committed to planting more trees than we harvest. Every year our forests grow by over 3,500 square miles - equivalent to an area the size of Cyprus. Forests act as huge carbon sinks. The total carbon sequestered in Europe's forests is over 9.5 million tonnes. |
Building with brick and block tends to have a massive negative effect on the environment. This is because it takes massive amounts of energy to manufacture bricks. However it is possible to use reclaimed and recycled bricks, which reduces the environmental impact. |
Justify chosen forms of Construction (Task 3 E)
The two forms of construction I chose were timber frame for the modern method and Brick and block as a traditional method.
Timber frame
The reasons I chose timber frame for my modern method of construction are;
- Quick to erect - reduces capital lock up.
- Lightweight - can be used on brownfield sites/sites with difficult land conditions.
- Modular components - are easy to transport.
- Engineered components - quality assured standards, reduce the need for site skills.
- Dry - gives a clean site and it's quick to decorate.
- Craning - can be craned in for tight inner city sites.
- Prefabricated - strict quality control, fewer post erection quality/ snagging problems.
- Design responsive - can go to 7 storeys.
- Superior sound performance - meeting all new regulations.
- Modular approach - excellent for volume build, social /student etc housing and hotels.
- Completed buildings - can be clad in stone, brick, render, tile etc. giving maximum “kerb appeal.”
- Sustainable construction - responds to the environmental agenda of many partnership projects and social housing procurers.
Brick and Block
The traditional method of brick and block was chosen as it is a durable common building material. It had a wide selection of bond patterns with different strengths to structural aspect as well as providing an aesthetically pleasing finish. Also a wide variety of bricks and masonry blocks are available to give and ideal finish. Brick and block work is also fire resistant to reduce the spread of fire and has a long life expectancy. Brick and block work has high sound insulation and thermal properties.
Compare the Properties of Steel and Timber (Task3 F)
The structural strength of timber is a measure of its ability to resist outside forces, such as compression, tension and shear. The density is reliable indicator of many structural and mechanical properties. There is a particularly strong relationship between density and compressive strength, bending strength and hardness and a fairly reliable relationship between density and stiffness.
Density ranges from an average of 160 kg per cubic metre for balsa to 104 0 kg per cubic metre for greenheart, with the most commonly used structural softwoods having a density between 450 and 550 kg per cubic metre.There is a marked difference in strength properties depending upon whether they are measured parallel to or perpendicular to the grain of the timber. The tensile strength of most timbers parallel to the grain is three to four times the compressive strength. The tensile strength parallel to the grain can be thirty times as high as perpendicular to it, while for compressive strength the ratio is of the order of six to one.
High tensile strength steel has a high tensile strength but a strain percentage of around 2.5%. Structural steel is formed to a British standard BS 4360 these are hot rolled formed sections. They can be connected by means of welding. This is and effective method of producing structural steel joints. Structural steel must also be able to with stand impacts imposed upon it. The steel members must be able to deal with temperatures and also if the steel member is overstressed it should yield rather than fail. Steel structural members should have high yield strength to for fill its purpose. There are various grades of steel.
Identify and Describe Three Internal and External Finishes (Task 3 G)
Internal
The internal finishes of a building is very important, as it has to suite the purposes of the building or that specific room.
Ceramic Tiles
Ceramic is distinguished by being easy to clean, dirt resistant and resistant to any kind of contamination. Ceramic tiles are cleaned simply with a damp cloth and should the surface be dirty or greasy, cleaning agents such as detergents or bleach may be added to the water. The very nature of ceramic surfaces prevents serious sticking and grease can be removed very easily. As a result, ceramic tiles are now widely used in bathrooms, kitchens, hospitals, laboratories, swimming pools, industrial facilities and so on, where they prevent dirt and odours from building up.
Once they are in place, ceramic tiles need no maintenance other than normal cleaning. Because they are resistant to sharp swings in temperature, chemical and biological agents and abrasion and are tough and scuff resistant, they have a very long life expectancy in buildings. Newly fixed tiles can remain untouched and unattended anywhere. This is why they are being used prolifically in so many places, particularly on façades of buildings, in public spaces, shopping centres and walkways. In addition, they are fireproof and therefore inhibit the spread of fire.
Wall Paint
The most common form of internal finish is plaster with a painted finish. The advantages of a painted finish is that the best color can be selected for the specific rooms. Also paint is not a permanent finish; this is because it can be rubbed down then re-painted with a different color to change the aesthetics of the room.
Painted walls create a very comfortable and warm feeling. However if the colors become faded or discolored then a touch up may be required.
Carpeting
Carpet creates a very warm and comfortable room; carpet also has very good sound insulation properties. Regular, but simple vacuuming, quick attention to spills and professional cleaning every 12 to 18 months is all it takes to keep up appearances.
It's a great non-slick walking surface that prevents slips and falls. It ensures that seniors and toddlers find sure footing. However carpet isn't suitable for all rooms, for example you wouldn't have carpet in a kitchen area or shower room.
External
External finishes are vital, as a building has to fit into the surrounding area, whilst also being attractive.
Timber Cladding
Timber cladding is an increasingly popular choice for finishing the outside of commercial and domestic buildings. Otherwise known as weatherboarding or siding, timber cladding is an attractive and economical way to finish the exterior of both new and old buildings. Woods such as larch and western red cedar provide a hardwearing, protective layer against the elements and they are excellent insulators.
Many different species of wood are suitable for exterior use because of their natural resistance to decay. Traditional British timbers such as oak, elm, chestnut, western red cedar and larch have been used for hundreds of years to protect houses from the elements. Imported timbers such as Canadian western red cedar and Siberian larch are increasingly being specified for a more modern, contemporary appearance.
These species of wood are available in a range of profiles from the more rustic waney-edge and feather-edge to the clean lines of the machined shiplap and halflap.
Pebble Dashing
Another finish that used to be popular for years is pebble dash, cement is applied to the walls and a machine is then used to throw the pebbles at the wall embedding them into the cement. In days gone by the only reason that people used to plaster the outside of their houses or use pebble dash was to cover up the bad workmanship of the block layers but now a days people have to work to set standards so that is no longer the case. However this is not a very fashionable way of creating an attractive external finish and it is very dated.
Rendering
Rendering is external plaster that is often used on brick and block work and is often painted. It can be aesthetically pleasing as well as giving added weather protection.
Render should be weaker towards the outer coats to allow a greater flexure on the out skin. Renders with exposed aggregates or rougher textures are les s likely to crack compared to smooth surfaces. When applying the render care should be taken allowing each successive coat to harden slowly as a weak mix will result in cracking.
Provision of the four Primary Services Utilities to the Buildings (Task 4A)
Compare the four services utilities in Terms of Installation and Maintenance Issues (Task 4B)
Water
In the installation of water pipes everything must comply with the Building regulations part G. This includes that all buildings must have a toilet, sink and all dwellings must have hot and cold water, a fixed bath or shower. Also all water services should have a minimum working pressure of 200 psi.
No water service should be installed when the service pipe is in line with a tree, fire hydrant, catch basin, or other obstruction. If the water service pipe is to be of concrete or pavement area a ‘D' box must be installed. The water service may be placed in the same trench with the sewer line if approval is given by the Water and Sewer Department, and all of the following conditions are met: The bottom of the water service pipe at all points shall not be less than 18 inches above the top of the sewer line at its highest point. The water service pipe shall be placed on a solid shelf excavated at one side of the common trench.
Gas
The gas regulations in this Country require the installer of any gas appliances or fittings to be competent and to do so with safety, they also recommend that all work should be carried out by a corgi registered gas fitter. The Health and Safety Executive, who control such things, have the power to enforce regulations against a diy installer if it can prove the installation was carried out in an unsafe way. This is not hard in the event of an accident!!
Where a pipe passes through a wall or concrete floor the pipe must be with in a sleeve or a pipe of a larger diameter. This is to accommodate for any building settlement. The space between the sleeve and the service pipe must be sealed with a fire resistant mastic sealant. At the end of the service pipe there is a metre control valve that stops the flow of gas to the dwelling. A gas service pipe must be 375 mm below the surface. Where the pipe joins the gas main there is a plug cork this is to allow the gas authorities to shut of the gas in case of an emergency.
Electricity
The national grid is huge cables carrying the power at 33,000 volt and above. The wires are suspended using pylons. The wires run across the country and branch off to local transformers. The local transformer reduces the voltage from 33,000 volts to 240 volts. This makes the electricity suitable for domestic distribution. The cables then run under ground to feed the dwelling in the area. The cable must be laid 750mm under roads and 450mm under open ground. The cable runs to the meter box (consumer unit) often on the out side of the property so the electricity supply can check the consumption. And the wires run in to the house from this point.
Drainage
There are 2 different types of systems when it comes to drainage in dwellings/buildings;
Combine- Foul and surface water pipes are joined
Separate- Foul pipes are separate from surface water pipes
Types of approved sewer pipe:
•Storm Sewer (sump pump leads) - minimum 3” Schedule 40 P.V.C.
•Sanitary Sewer Leads - 4” minimum from property line to house, minimum of 6” in road right-of-way. SDR 23.5, Schedule 40 P.V.C., ABS plastic, SDR 35 P.V.C. (in sandy conditions only).
All pipes that are used should have the marking of an approved testing agency, such as N.S.F., A.S.T.M., etc.
To maintain these pipes and keep them in good condition here is a list of what to do;
•Cleanouts should be installed immediately inside or outside of the building.
•Cleanouts should be installed at a minimum of every 90 feet or such that the total distance, including the cleanout riser and sewer lead, does not exceed 100 feet.
•All outside cleanouts must be brought up to finish grade.
•Cleanouts shall be installed at every change of direction greater than 45 degrees.
(90 degree elbows are prohibited).
On the actual building the gradient of the roof gutters must be 1:360 so that the water does not build up. To make sure these are in good condition and are not harmed during sewage works all excavators and contractors tapping sewer mains should be bonded with a surety bond and a cash bond.
Limitations Imposed by Legal, Health and Safety Requirements (Task 4C)
Electricity
The Electricity at Work Regulations 1989 imposes a legal framework specific to electrical safety which is applicable to all work activities with electricity. There are no voltage limits and the scope of the Regulations extends from the smallest, simplest battery systems such as torches etc, to the national transmission systems. The aim of the Regulations is to prevent injury from whatever source of electrical energy.
The Electricity at Work Regulations 1989 require heads of departments to ensure that electrical systems and equipment for which they are ultimately responsible are designed, operated, maintained, modified and extended in such in a way which avoids danger.
Examples of the regulations are as follows:
Regulation 4;
All electrical systems shall be constructed and maintained to prevent danger. All work activities are to be carried out so as not to give rise to danger.
Standard of duty - reasonably practicable.
Regulation 8;
Equipment must be earthed or other suitable precautions must be taken e.g. the use of residual current devices, double insulated equipment, reduced voltage equipment etc. Standard of duty - absolute.
Regulation 12;
Where necessary to prevent danger, suitable means shall be available for cutting off the electrical supply to any electrical equipment.
Standard of duty - absolute.
Note: drawings of the distribution equipment and methods of identifying circuits should be readily available.
Note: ideally, mains signed isolation switches should be provided in practical work areas.
Gas
Badly installed or un-serviced appliances can emit carbon monoxide, caused by incomplete combustion, and the danger is compounded when ventilation flues are blocked. The lethal gas has no smell or taste and at low dose will produce symptoms of dizziness, nausea and fatigue that are easily mistaken for flu and other common illnesses. People asleep are most at risk when they leave gas fires on at night. Combustion uses up oxygen in the room increasing the dose of carbon monoxide breathed from a faulty appliance.
Legislation dealing with gas appliances and installations came into force on 31 October 1994 and was amended in 1998. By law
- Anyone carrying out work on gas appliances or fittings must be competent and registered with CORGI (Council for Registered Gas Installers) To check your contractor is registered with CORGI call 01 256 372300. Only competent people can carry out work on gas appliances or fittings.
- You must not use any gas appliance or fitting which you know or suspect to be unsafe. All CORGI registered installers have been asked to disconnect any appliance or fitting which would be a threat to safety
- Landlords are now required to have all gas appliances and flues checked once a year for safety. This work should be carried out by a competent installer registered with CORGI. Tenants have the right to see proof that these checks have been done.
Water
Water service systems must comply with the Water Supply (Water Fittings) Regulations 1999, and any subsequent amendments. OUED will ensure that only competent contractors are engaged for maintenance, repair, or replacement programmes and those only approved materials are used. OUED will ensure that cold water storage is minimised, and this normally should be no greater than one working day's average water consumption. Water use in buildings should be recorded annually. OUED will ensure that suitable measures are in place to protect cold water storage tanks and prevent excessive temperature increases in the cold water supply.
Storage calorifiers and recirculating hot water systems must store hot water at a minimum temperature of 60°C and deliver hot water of at least 50°C to the outlet. OUED is responsible for monitoring the temperature of these outlets in accordance with the regime set out in Table 1. Consideration of the Legionella risks associated with calorifiers and central hot water systems must be taken into account during any hot water replacement programme. Wherever practicable, hot water storage vessels should be replaced with plate heat exchange systems or direct gas fired hot water heaters.
Section 1 1.9- A urinal with a flushing apparatus should go through a grating, a trap and a branch pipe to a discharge stack. This keeps the room hygienic and stops any smells appearing.
Section 2 2.2- A bath or shower should have a supply of hot water in any dwelling. This may come from a unit water heater or a central source. This also keeps the hygiene up in a dwelling.
Section 4 4.4- Any un-vented hot water storage vessel with a power input of more than 45kW should have the appropriate number of temperature relief valves. These valves should be factory fitted to the vessel so the temperature is right when it comes out the tap.
Drainage
The Building Act 1984
Foul drainage Section 2- Foul drainage should be connected to a public foul or combined sewer wherever this is reasonably practicable. The sewer should be in satisfactory condition and have sufficient capacity to take the additional flows. Where levels do not permit drainage by gravity a pumping installation should be provided so that the drains do not get blocked.
Depth of pipe cover 2.27- The depth of cover will usually depend on the levels of the connections to the system, the gradients at which the pipes should be laid and the ground levels. Pipes also need to be protected from damage so that no leakages are found.
Pipe gradients and sizes 2.29- Drains should have enough capacity to carry the flow. The flow depends on the appliances connected and the capacity depends on the size and gradient of the pipes. It should be at a gradient so that nothing gets stuck which may block the pipe up.
Electrical and Water Services Required for the Manager's office Task 4D
Water
The manager's office will be supplied with an indirect supply of hot and cold running water. The office will have its on washroom, which will consist of a toilet and sink. The washroom will be separate to the rest of the office space to prevent smells.
An indirect water system is where the water comes in to the building via the water mains. The pipe branches off to supply one tap in the building for drinking water and must not be stored. The pipe will then feed the boiler, on the way to the storage tanks in the loft, where it will be heated. The water will be distributed to other taps and appliances after the storage tank. This indirect system is more expensive than a direct system however it reduces the risk of back siphonage. The system must comply with British standards.
Manager's office and Toilet layout
Electrical
The manager's office will be supplied with 4-6 plug sockets which will be used for the computer, printers and faxes etc. There will also be a server socket, which will link the computer up to the motels system and internet. A phone line will also be supplied for the use of a telephone and fax machine. The room will also be supplied with adequate lighting and a dimmer switch; this is to allow for extra comfort for the manager.
The electricity will be supplied using a radial circuit. This is the most common form of circuit used in domestic dwellings. Ring circuits always run in 2.5mm² and are protected by a 30 amp fuse. Theoretically there is no limit to how many sockets can be fitted providing it does not serve a floor area of more than 100sq m.
Task 5 Site security and storage facilities;
In order to prevent unauthorized access a site boundary fence will be erected, this would make it harder for thieves and vandals to get onto the site therefore reducing the cost of new equipment. All materials and machinery will be securely locked away in a safe place, as well as preventing theft it would also reduce the risk of people being hurt accidentally by falling objects.
Site condition;
It is important that the construction site is kept in a good, clean, working condition. To ensure this many skips will be placed around the site, the skips will be coloured in order of what materials should be placed in them this will make it easier to recycle them. All vehicles leaving the site will be cleaned to ensure that the local roads and drainage systems aren't damaged; this will be done on an impermeable surface so that silt does not run into the local water system. Any rubbish that does escape into the local area will be cleaned up by road sweeps which will be employed to ensure that area is kept as clean as possible.
Site traffic;
As with all construction sites there should be a specific traffic management system in place that takes into consideration the local people. This should aim to makes sure all deliveries and other site traffic should take place outside the rush hour to reduce the disruption caused to the local area. Delivery of goods will not take place between the hours of 8-9 and anytime after 3 o'clock.
Damage to local property;
It is commonly known that an area can become visibly damaged when construction is taking place. This can be prevented by designating a safe spot for the vehicles to turn around. We will also employ a road sweep that will regularly attend the area keeping it clean and safe by reducing trip hazards. Any damage caused to local property should be reported to the site manager.
Local noise pollution;
Building sites are renowned for being noisy places. As well as this being a nuisance it is also a health and safety hazard as people's ears can be damaged. To prevent this from happening we will erect sounds screens which will reduce the amount of noise created. There will also be a schedule in place which gives the firm windows of time in which excessive noise can be created; this will be discussed with the local people.
Air quality;
Outdoor air pollution has an impact on indoor air quality and designers of buildings in urban areas need to take this into account when considering natural ventilation for a new building or when sitting intakes for air conditioning systems. Filters in mechanical ventilation systems are usually designed to remove particles; removing gaseous pollutants can be complicated and costly, so obtaining better quality air is to be preferred if possible.
Asbestos;
All asbestos will be removed from any construction site that we are working on. A specialist team will be trained up and given the correct equipment to carry out his task safely. All waste asbestos will be disposed of safely in an appropriate waste management site.
Storm water;
Storm water run-off from construction sites is a significant, and frequently underestimated, source of pollution. Activities, such as clearing, grading, and excavating, disturb or expose soil leaving it highly susceptible to weather erosion for prolonged periods.
This surface erosion is often more than 150 times greater than before works began, with sediment run-off rates typically 10 to 20 times greater than those from agricultural lands, for example. Consequently, during a short period of time, building sites can contribute more sediment to waterways and drainage systems than would normally be deposited over several decades.
This not only results in increased public spending on activities such as storm water sewer maintenance and dredging of waterways, but the deposited silt particles (which may be tainted by construction site pollutants) can also cause serious environmental harm to aquatic habitats.
In order to ensure that the company follows these guidelines someone will be given the role of an environmental assure. It's in any firm's best interest to comply with the guidelines put in place as this will help prevent complaints from the local people and would ensure that the construction took place without any unnecessary hitches.
Task 6
a) Here is the calculation of the plan area of a pad foundation to an axial loaded column.
Firstly, the area of the foundation = Load .
Bearing Capacity
Therefore, 195KN = 0.951m2
205 KN/m2
This means that the pad foundation looks like this;
b) Next is the calculation of the width and depth required for a traditional strip foundation with a cavity wall of 275mm.
The area of the foundation is equal to the load divided by the bearing capacity, which is also equal to the width of the found.
. . Width = 45
80
= 0.5625m
= 562.5mm
To get the projection of the foundation you need to take the wall thickness away from the width and divide the answer by 2.
562.5 - 275 = 143.75mm
2
However, the projection must be at least 150mm, as shown on the drawing.
We provide a professional essay writing service that thousands of our customers use as an effective way of improving their grades, improving their research and saving them lots of time.


